AVENTA

Current Project Phases

Engineering, Installation / Operation

Role Definition

Activity 1: Pre-piling NOY T&I Activities

  • Evaluation Method statements T&I Contractor
  • Evaluation delivery Pin piles Flushing
  • Documents for notifications start on site
  • Follow up refurnishment pre-piling template and casing
  • Follow up pre-piling activities
  • MWS coordination
  • As built documents / surveys

Activity 2: T&I NOY Jacket & Topside Installation

  • Evaluation Load out and seafastening jacket & OSS engineering and T&I method statements (Navantia and CDA)
  • Check sea-fastening / Barges and Load out
  • Documents for notifications jacket and topside Installation
  • Follow up jacket & topside Installation
  • MWS coordination
  • As built documents

Activity 3: T&I TRE Jacket & Topside Installation

  • Evaluation Load out and seafastening jacket & OSS engineering and T&I method statements (Navantia and CDA)
  • Check sea-fastening / Barge and load outs
  • Documents for notifications jacket & Topside Installation
  • Follow up jacket and topside Installation
  • MWS coordination
  • As built documents

In order to ensure a continuous communication between the Client and the Service Provider, a series of meetings will be organised by Client throughout the duration of the Contract. Attendance and participation to these meetings will be key to ensure communication and alignment between the parties.

Coordination Meetings

Among the recurrent meetings organised by Client, the Service Provider may be requested to attend to monthly coordination meetings. These meetings will aim at:

  • Measuring performance of the Contract execution,
  • Reviewing upcoming needs for additional activities and termination of on -going activities as the case may be,
  • Holding discussions on challenges, difficulties, lessons learnt.

From time to time, the coordination meetings could be face -to-face meetings held in the Client’s offices in Paris-La Défense (France), Flushing (UK), Saint Nazaire (France), Puerto Real (Spain). However, if jointly agreed, those meetings will normally be held through conference call or teleconference call.

Note:

  • The agenda of coordination meetings is at this stage preliminary and will be fine -tuned all along contract execution,
  • The frequency of these meetings may vary (increased, decreased or even suspended) during periods when exchanges do not seem to be necessary.

Adhoc Meetings & Workshops

In addition, various ad -hoc meetings or workshops will also take place. If Client judges it relevant, the Service Provider will be requested to attend to these ad -hoc meetings.

Conditions

Place of performance : Paris office Noirmoutier + Dieppe le Treport + St Nazaire + Remote

Others informations

Type of contract: Permanent or Contractor

Seniority level : Senior Engineer, Lead Engineer

Type of project : OffSHORE WIND Farm

Countries : France

Location : Paris Area + On site mission

Upload your CV/resume or any other relevant file. Max. file size: 5 GB.


You can apply to this job and others using your online resume. Click the link below to submit your online resume and email your application to this employer.

Related Jobs
  • Torrid Fashion company
    Full Time
    St. John's, NL, Canada

    Are you interested in being a Sales Associate at Torrid Fashion company? Suppose you are interested; this job posting is for you. You also need to know more procedures that guarantee employment, such as the potential requirements, skills engagement,
  • Walmart Retailer corporation
    Full Time
    221 RIVER ST, HOBOKEN, NJ 07030, United States of America

    Senior Manager, Digital Media Partner Marketing has become one of the most attractive positions in the job sector as it produces potential formats like benefits and experiences. You want to know more procedures that guarantee employment; the requir
  • Star Surf Camps
    Full Time
    Moliets, France

    Head of Kitchen Moliets, France About The Company. Star Surf Camps started with one small surf camp in France during the summer of 2010 and have since expanded across Europe, proudly welcoming back guests and returning staff year after year. At
error: